S8 - under construction
S8 under construction
More [+]
S8 under construction
S8 dual carriageway under construction.
The works are still going on.
Investor: GDDKiA
General Contractor: Przedsiębiorstwo Usług Technicznych "Intercor" Sp. z o.o.
P.B.I. PEBIS sp. z o.o. has started to construct storm water network on the S-8 expressway section from Przeszkoda to Paszkow.
We will construct storm water line of:
1. PP DN160-DN800 - 6340m
2. PEHD DN150-DN450 - 345m
3. PCV DN200-DN400 - 73m
4. rainforcement chamber DN1200-DN3200 - 231 item
5. concrete chamber DN500 - 247 item
6. underground storage reservoirs
7. sewage treatment plant